當(dāng)前位置: 東方風(fēng)力發(fā)電網(wǎng)>看資訊 >海外風(fēng)電 > MHI Vestas launches 9.5MW V164 turbine in London

MHI Vestas launches 9.5MW V164 turbine in London

2017-06-08 來源:windpower 瀏覽數(shù):1748

 

"Applying the 9.5MW turbines means 16 fewer machines, plus their associated substructure, cables and installation costs. The individual substructure and turbine Capex and Opex are essentially the same, but there is modest AEP penalty at project level," Andersen said.

"in 2009, when offshore wind project Capex was very high, the total Capex saving of deploying fewer higher-rated turbines would have been modest. But now that it is much lower overall, the relative share of installation is substantial, and so has a much larger positive impact on LCOE."

Lean production

In August 2013, Windpower Monthly reported from Lindø on the building of a V164 prototype. Assembly was taking place in a largely empty former shipyard hall, a makeshift facility with a rough concrete floor and temporary steel sheets supporting the massive prototype assembly structure. Today’s multiple extensively upgraded halls dedicated to V164 serial production mark a sharp contrast.

Early days… The company's production facilities have changed a lot since this V164 prototype was made in Lindø in 2013

All components and sub-assemblies arrive by road in the factory warehouse, where they are checked and registered. Some critical components, such as the huge dark-blue coated gearboxes, are fitted with accelerator sensing devices. These record all acceleration forces imposed on the product during transportation and handling, and from manufacturered product to the installation of complete nacelles in a wind project.

The vast assembly hall is subdivided into a left part part for large components and sub-assemblies, and overhead cranes for internal hoisting, with the right part reserved for nacelle completion.

A key characteristic is a lean production process, still in development, based on Japanese Kaizen principles first developed by Toyota, and which includes multiple temporary fixed "tack" positions for the nacelles until completion. An air-conditioned tent is dedicated to creating a controlled environment for main shaft assembly. Individual main shafts are put inside in vertical position for shrink-fitting the largest front-bearing inner ring, followed by hoisting-in and lowering the cast housing over the shaft. The next step is shrink-fitting the rear-bearing inner-ring plus mounting a locking ring. The assembly process is finalised by 24-hour flushing with special oil to remove any metallic particles and other impurities.

"We decided on an oil-lubricated main shaft with oil filtration for optimal lubrication performance and bearing life, and minimal bearing pre-load variations during operation," said Andersen. "Full main shaft units can be exchanged without having to remove the rotor, and other drivetrain main components can also be individually replaced."

V-164 nacelles are huge viewed from the outside, and spacious and service-friendly inside. An unusual design feature is the upside-down mounting of the yaw motors inside the tower’s top section. It enables easy service access from an intermediate service platform, and more space with fewer obstructions inside the nacelle.

Continuous adjustment

Proven in many generations of Vestas turbines since the V27-225kW model is the yaw brake system comprising opposing steel and Teflon rings, and multiple spring-loaded friction pressure points. The solution is designed to last 25 years and enables continuous rotor adjustment to wind direction changes.

A distinct design achievement is the compact "closed" hub for enhanced stiffness, which incorporates two approximately 700kg pitch actuators for each blade, individually removable with the aid of a telescopic inboard crane. The pitch bearings feature 4.6-metre bolt-circle diameter, which is large compared with "only" 4.2 metres for the 8.5-metre longer blades of the Adwen AD 8-180 turbine.

The V164 is equipped with load-based individual pitch control (IPC). "Blade root loads are continuously measured during each rotor revolution and used in the control of the turbine," explained Andersen.

【延伸閱讀】

標(biāo)簽:

閱讀上文 >> “清潔能源·創(chuàng)新使命峰會”在北京隆重開幕
閱讀下文 >> 國家能源局公布12個(gè)“2017年北方地區(qū)冬季清潔取暖試點(diǎn)城市”

版權(quán)與免責(zé)聲明:
凡注明稿件來源的內(nèi)容均為轉(zhuǎn)載稿或由企業(yè)用戶注冊發(fā)布,本網(wǎng)轉(zhuǎn)載出于傳遞更多信息的目的,如轉(zhuǎn)載稿涉及版權(quán)問題,請作者聯(lián)系我們,同時(shí)對于用戶評論等信息,本網(wǎng)并不意味著贊同其觀點(diǎn)或證實(shí)其內(nèi)容的真實(shí)性;


本文地址:http://www.biz8848.com/news/show.php?itemid=47934&page=3

轉(zhuǎn)載本站原創(chuàng)文章請注明來源:東方風(fēng)力發(fā)電網(wǎng)

按分類瀏覽

點(diǎn)擊排行

圖文推薦

推薦看資訊

主站蜘蛛池模板: 男女国产一级毛片| 高潮毛片无遮挡高清免费| 婷婷四房综合激情五月在线 | 亚洲欧美国产日本| 精品一区二区久久久久久久网站| 国产亚洲精品美女久久久久| 日本三级韩国三级美三级91| 国内精品久久久久国产盗摄| www.日本在线| 岳双腿间已经湿成一片视频| 久久久久久久女国产乱让韩| 日韩高清国产一区在线| 亚洲区视频在线观看| 欧美视频在线观看免费| 免费a级毛片网站| 精品欧洲av无码一区二区三区| 国产乱人视频在线观看播放器| 黄色免费网址大全| 国产欧美日韩精品一区二区三区 | 最近中文字幕无| 国产精品国产香蕉在线观看网 | 四虎成人精品国产永久免费无码| 韩国电影中文字幕在线观看 | 久久96国产精品久久久| 日韩美女在线视频网站免费观看| 亚洲一区二区三区91| 欧美大荫蒂毛茸茸视频| 亚洲欧美日韩国产精品26u| 波多野结衣被躁五十分钟视频| 伊人久久久久久久久久| 皇上往下边塞玉器见客| 午夜成人在线视频| 美女扒开内裤羞羞网站| 国产av人人夜夜澡人人爽| 色综合久久天天综合观看| 国产亚洲人成网站在线观看| 香港三级韩国三级人妇三| 国产女人在线观看| 高清国产精品久久| 国产国语对白露脸| 高清一区高清二区视频|